Year: 2006
Conceptual design
Kfoury Metals Co Port
- Industrial port for metallurgic export
- Main quaywall (L=50.00m @-10.00m MSL)
- Secondary quaywall (L=95.00m @-7.50m MSL)
- RC Platform (4,750m2)
Year: 2007 - 2008
Design / Surveying / Permitting
- Main quaywall (L=50m @-10.00m MSL) / Underwater concrete blocks (Gravity QW)
- Secondary quaywall (L=95m @-7.50m MSL) / Underwater concrete blocks (Gravity QW)
- RC Platform (9,397m2)
- Marine accessories (Mooring Bollards, Fenders)
- Infrastructure (Electrical and water supply fittings)
- Water intake pipes
- Rocky dredging (Blasting)
- Topographic survey (10,000m2)
- Bathymetric survey (150,000m2)
- Tender Documents / Drawings / BoQ / Permitting
Year: 2009 - 2010
Contractor assistance
- Contractor : MARCONTRACTING
- Duration : 2 years
Year: 2011 - 2012
Design / Permitting
- Reclaimed area (2,800m2)
Year: 2013
Conceptual Design / Permitting
- Port Storage structure (713m2)